Justin Clancy placeholder no image

Media Release: Table Top community keeps up push for safer Hume intersection

August 11, 2026
Justin Clancy placeholder no image

Media Release: Water Infrastructure Shortfall Holding Back Regional Growth

August 20, 2026
Justin Clancy placeholder no image

Media Release: Table Top community keeps up push for safer Hume intersection

August 11, 2026
Justin Clancy placeholder no image

Media Release: Water Infrastructure Shortfall Holding Back Regional Growth

August 20, 2026

Media Release: Wymah Pumped Hydro Site Will Not Progress

WYMAH PUMPED HYDRO SITE WILL NOT PROGRESS

 

Member for Albury Justin Clancy has welcomed confirmation from WaterNSW that the potential pumped hydro site at Hume Dam in the Wymah Valley will not progress to the next stage of its Long Duration Storage Program.

Mr Clancy said the decision provided welcome certainty for local residents and landholders.

“I welcome WaterNSW’s decision not to progress the Wymah site,” Mr Clancy said.

“When I met with WaterNSW and Greater Hume Council last month, I raised a number of concerns that needed to be properly considered, including the potential for more than 30 kilometres of transmission infrastructure across private land, as well as questions around Lake Hume water levels, sedimentation, environmental impacts and overall viability.

“The purpose of pre-feasibility work is to determine whether a potential site stacks up before progressing further. WaterNSW has now advised that other sites offer greater overall value and are better aligned with the objectives of the program.

“Most importantly, this decision provides certainty for the Wymah community and surrounding landholders.

“I also acknowledge the timely response from WaterNSW following concerns raised by the community, and the advocacy of Greater Hume Council in ensuring the interests of local residents and landholders were heard throughout this process.

“I appreciate WaterNSW’s willingness to brief my office and Greater Hume Council, answer our questions and provide a clear outcome from their investigations.

“This is the sort of early engagement and transparency communities should expect when major infrastructure opportunities are being considered.”